Case study
Residential Interior
Rovinj, Croatia

Scope
- Kitchen installation
- Wardrobes
- Wall panels
- Interior doors
- Bedroom furniture
- Office furniture
Project duration
11 installation days
Team
3 installers
Installation challenges
A complete bespoke interior delivered in several shipments, with uneven site walls and a worktop that had to be templated on site while other trades were still finishing.
Technical solutions
The team sequenced the installation around the delivery schedule, verified critical dimensions before assembly, adjusted fillers and scribes to the existing structure and coordinated worktop templating directly with the manufacturer.
Final result
All rooms handed over with aligned fronts, adjusted hardware, photographic documentation and a closed snag list.